Environmental Permit Matrix

Question-to-Permit Relationships

#Question
01Traverse Land managed by the United States Bureau of Land Management (BLM)?
 National Environmental Policy Act (NEPA) Chapter 8 Screening Analysis, Clark County Regional Flood Control District Supplemental Environmental Impact Statement; Categorical Exclusion determination or Facility-Specific Environmental Analysis. Decision Document Categorical Exclusion, Finding of No Significant Impact [FONSI] or Record of Decision [ROD]
 BLM Right of Way (ROW) Temporary Use Permit (TUP)
 BLM ROW Grant
02Traverse Land managed by the United States Bureau of Reclamation (USBR)?
 NEPA Decision Document (Categorical Exclusion, FONSI or ROD)
 USBR Right of Entry Temporary Use Letter
 USBR Land Use License
03Traverse Tribal Lands?
 NEPA Decision Document (FONSI, Categorical Exclusion, or ROD)
 Permission for use of tribal land.
03aResult in any discharge into "waters of the United States (US)" on tribal lands as defined by Section 404 of the Clean Water Act (CWA)?
 CWA, Section 401 Water Quality Certification on tribal lands
 National Pollutant Discharge Elimination System (NPDES) General Stormwater Permit for Construction on tribal lands
04Involve discharge (placement) of dredged or fill materials into "waters of the US" as defined by Section 404 of the CWA. Ephemeral washes that drain into a "waters of the US" are under the U.S. Army Corps of Engineers (USACE) jurisdiction?
 Section 404 of the Clean Water Act (CWA) Permit
05Potentially result in direct or indirect impacts to federally listed Threatened and Endangered Species and/or associated habitat?
 ESA Section 7 Consultation with USFWS and Biological Assessment (BA)
06Result in temporary activity or permanent use on Nellis Air Force Base (NAFB) property?
 Base Civil Engineering Work Clearance Permit
07Result in any potential effect to historic properties?
 Section 106 NHPA of 1966
08Disturb wildlife and/or wildlife habitat?
 Written Approval
09Effect (referred to as "salvage and removal") more than 5 native cacti and/or yucca (for the purpose of moving to another location and/or selling)?
 Native cacti and yucca commercial salvaging permit and shipping or transportation permit
09aWould the proposed project require disturbance of any native plant species and/or native plant species habitat regarded as threatened with extinction (NRS 527.260 - 527.300) on private or federal land.
 Conditional Permit for Disturbance or Destruction of Critically Endangered Species
10Require or result in any discharge into "waters of the US" as defined by Section 404 of the CWA?
 CWA, Section 401 Water Quality Certification
10aRequire or result in any discharge into "waters of the US" as defined by Section 404 of the CWA?
 CWA, Section 401 Water Quality Certification
 NPDES General Stormwater Permit for Construction
11Disturb 5 acres or greater, and discharge storm water runoff from the construction site into a municipal separate storm water sewer system, or “waters of the US?"
 NPDES General Stormwater Permit for Construction
12Cause a temporary point-source discharge to surface water, i.e. natural channel, roadway or storm drain for a duration less than 6 months. (construction dewatering)
 NPDES Temporary Discharge Permit
13Require equipment to be used and maintained within surface bodies of water?
 Temporary Permit for Working in Waterways (Formerly known as a "Rolling Stock Permit")
14Require temporary dewatering wells during construction activities, require testing and monitoring wells?
 Waiver (dewatering well, monitoring well, and/or testing well waiver)
15Require Nevada Department of Transportation (NDOT) Right-of-way (ROW) encroachment or construction activities within NDOT ROW?
 NDOT ROW Encroachment Permit
15aRequire traffic barricade within NDOT ROW?
 Traffic Barricade Plan Approval
16Require storage of 5 gallons or more of flammable liquid inside or 10 gallons or more of flammable liquid outside for 30 days or more?
 Hazardous Material Permit or Roving Permit
16aRequire combustible liquid storage tanks to be moved to different staging areas on the project site during construction activities?
 Hazardous Material Permit or Roving Permit
17Require storage of 10 gallons or more of combustible liquid inside or 25 gallons or more of combustible liquid outside for 30 days or more?
 Hazardous Material Permit or Roving Permit
17aRequire combustible liquid storage tanks to be moved to different staging areas on the project site during construction activities?
 Hazardous Material Permit or Roving Permit
18Require any grading or other land-disturbance activities within Clark County?
 Dust Control Permit
19Require site drainage associated with construction requiring more than 2 acres within Clark County ROW?
 Drainage Study Approval
20Require activity within Clark County ROW?
 Off-site Construction Permit
 Encroachment Permit
21Result in a discharge of water in Clark County ROW?
 Encroachment Permit (Discharge Water)
 Traffic Barricade Plan Approval
22Result in impacts to traffic access and/or circulation in Clark County ROW?
 Traffic Barricade Plan Approval
23Require site grading activities in Clark County?
 Grading Permit
 Pad Certification for Grading and Earthwork
 Soils Report Submittal
24Require additional temporary stock piling of earth materials on USBR, County, or private lands not covered under the Clark County Grading Permit?
 Conditional Grading Permit
25Require construction of on-site and off-site temporary signs (other than those required by dust control permit or signs located in public ROW)?
 Temporary Sign Permit
26Require construction of perimeter block wall or fence?
 Block Wall/Fence Permit
27Require Landscaping?
 Landscape Certification for Grading and Earthwork
28Result in disturbance of previously undisturbed land – related to off-site construction activities within Clark County jurisdiction?
 Multiple Species Habitat Conservation Plan (MSHCP) Compliance Desert Tortoise “Take” Permit and collection of tortoise habitat remuneration fees.
29Require the use of above-ground generator fuel tanks during construction?
 Above Ground Generator Permit
30Require blasting for construction of facility?
 Blasting Permit
30aWould the proposed project require use/storage of chemicals or fuel onsite during construction?
 Flammable/Combustible Liquid Aboveground Storage Tanks
30bWould the project require a mobile fueling unit?
 Mobile Fuelers
31Require construction within jurisdiction of the City of Las Vegas?
 Plans check
31aResult in site drainage associated with construction of a new facility within jurisdiction of the City of Las Vegas?
 Drainage Study Review/Approval
31bRequire underground construction on private property or within City of Las Vegas ROW?
 Excavation Permit
31cRequire off-site construction activity within a City of Las Vegas ROW?
 Soils Report Submittal
31dRequire off-site improvements within a City of Las Vegas ROW?
 Construction Permit
31eRequire on-site grading activities?
 Grading Permit
31fRequire Temporary stock piling of earth materials on private or federal parcels not covered by grading permit?
 Temporary Stock Pile Permit
31gRequire perimeter block wall or fence?
 Block Wall/Fence Permit
31hRequire traffic barricade?
 Traffic Barricade Plan Approval
32Require construction within jurisdiction of the City of Henderson?
 Plans Check
 Excavation Permit
 Barricade Plan Approval
32aResult in public improvements?
 Revocable Permit and Encroachment Plan Approval
 Interlocal Contract
32bRequire topsoil disturbance within a flood zone and/or greater than 2 acres?
 Grading (Floodplain) Permit
32cRequire blasting within City limits?
 Blasting Permit
32dRequire use\storage of chemicals or fuel onsite during construction?
 Above-ground storage tank permit for flammable liquid
33Require construction within jurisdiction of the City of North Las Vegas?
 Plans check
33aResult in site drainage associated with grading and construction?
 Drainage study review and approval
 Grading and Drainage Permit
33bRequire off-site construction, excavation, installation, or occupancy within a City of North Las Vegas ROW?
 Off-site construction permit
33cRequire on-site construction of any structure?
 Building Permit
33dRequire traffic control in public ROW?
 Traffic Control Plan
34Require construction, excavation, installation, or occupancy in or near AT&T ROW?
 Coordination only. No permit required.
35Require construction, excavation, installation, or occupancy in or near Cal-Nev ROW?
 Coordination only, Occupancy Permit if required.
36Require construction, excavation, installation, or occupancy in or near Nevada Power ROW?
 Coordination only. No permit required
37Require construction, excavation, installation, or occupancy in or near Sprint ROW?
 Coordination only. No permit required.
38Require construction, excavation, installation, or occupancy in or near Southwest Gas ROW?
 Coordination only. No permit required
39Require construction, excavation, installation, or occupancy in or near Kern River Gas ROW?
 Encroachment Permit
40Require activity or occupancy within Southern Nevada Water Authority (SNWA) ROW?
 Occupancy Permit
41Require activity or occupancy within Union Pacific Railroad (UPRR) ROW or easements?
 Environmental Access and Occupancy Permit for Railroad ROW
 Pipeline Crossing Agreement
 Contractor's Right-of-Entry Agreement
 Drainage and Waterway Encroachment
42Require activity or occupancy on private property?
 Encroachment and occupancy approval from Private Owners