Environmental Permit Matrix

Permit Details

BLM ROW Grant
Category:Federal Permits
Issuing Agency:BLM Division of Lands, 4701 N. Torrey Pines Dr., Las Vegas, NV 89130-2301
Contact:Mark Chatterton, Assistant Field Manager, Office: 702-515-5000, Fax: 702-515-5023
Regulated Activity:Required for long-term use of BLM land or BLM ROW.
Prerequisite(s):Plan of Development (POD) with legal descriptions of project and alignment drawings, Project-specific Analysis, EA or EIS is required. Issuance of the ROW Grant is dependent on the decision for a NEPA document and approval of all federal, state, and local permits. Issuance of the BLM ROW Grant is required prior to construction notice to proceed (NTP).
Processing Time:Depends on projects complexity
Fees:Project specific
Submittal:SF-299, POD, tiered EA, EA / EIS.
When To Submit:Design phase
Who Submits:Project proponent
Who Receives:Project proponent
URL(s):http://www.blm.gov/wo/st/en/prog/energy/cost_recovery_regulations/grant_administration.3.html