| Category: | Federal Permits |
| Issuing Agency: | BLM Division of Lands, 4701 N. Torrey Pines Dr., Las Vegas, NV 89130-2301 |
| Contact: | Mark Chatterton, Assistant Field Manager, Office: 702-515-5000, Fax: 702-515-5023 |
| Regulated Activity: | Required for long-term use of BLM land or BLM ROW. |
| Prerequisite(s): | Plan of Development (POD) with legal descriptions of project and alignment drawings, Project-specific Analysis, EA or EIS is required. Issuance of the ROW Grant is dependent on the decision for a NEPA document and approval of all federal, state, and local permits. Issuance of the BLM ROW Grant is required prior to construction notice to proceed (NTP). |
| Processing Time: | Depends on projects complexity |
| Fees: | Project specific |
| Submittal: | SF-299, POD, tiered EA, EA / EIS. |
| When To Submit: | Design phase |
| Who Submits: | Project proponent |
| Who Receives: | Project proponent |
| URL(s): | http://www.blm.gov/wo/st/en/prog/energy/cost_recovery_regulations/grant_administration.3.html |