| Category: | Utility Services Permits\Coordination |
| Issuing Agency: | Cal-Nev Pipeline, 5049 Sloan Lane, Las Vegas, NV 89155 |
| Contact: | Vern Lacro Office: 702-643-9130 |
| Regulated Activity: | Construction, excavation, installation, or occupancy in or near a Cal-Nev ROW. |
| Prerequisite(s): | Submit preliminary design with a letter of notification. The Cal-Nev inspector should be notified 48 hours prior to construction. Coordination with Cal-Nev would be required if the project results in Cal-Nev ROW encroachment. |
| Processing Time: | 21 days |
| Fees: | None |
| Submittal: | Letter of Notification and Preliminary design with project location |
| When To Submit: | Design phase |
| Who Submits: | Design Engineer |
| Who Receives: | Design Engineer |
| URL(s): | None available |