Environmental Permit Matrix

Permit Details

Contractor's Right-of-Entry Agreement
Category:Utility Services Permits\Coordination
Issuing Agency:1.) Union Pacific Railroad (UPRR), Contract and Real Estate Department, 1416 Dodge Street, Room 1100, Omaha, NE 68179-1100 2.) 1800 Farnham St, Omaha NE 68102
Contact:John Devish Manager of Contracts Office: 402-544-8563
Regulated Activity:Construction activities within UPRR easements or ROW.
Prerequisite(s):UPRR and Project proponent negotiate agreement. Agreement signed and submitted by Project proponent. Project proponent and/or contractor submits certificate of insurance and fee payment.
Processing Time:10 day notification prior to survey or construction activities in UPRR ROW.
Fees:$500.00
Submittal:Agreement, certificate of insurance, and fee
When To Submit:Construction phase
Who Submits:Contractor
Who Receives:Contractor
URL(s):http://www.uprr.com/reus/encroach/encguide.shtml