| Category: | Federal Permits |
| Issuing Agency: | USBR Lower Colorado Region, P.O. Box 61470, Boulder City, NV, 89006-1470 |
| Contact: | Dave Curtis, Office: 702-293-8132 |
| Regulated Activity: | Required for long-term use of USBR land or USBR ROW. |
| Prerequisite(s): | A letter requesting right-of-use for proposed project segment within USBR Land is required. Applicant can apply as soon as there is a complete proposal, legal descriptions of project, alignment drawings, and a NEPA decision document. Issuance of the ROW Grant is dependent on the decision for the NEPA document and approval of all federal, state, and local permits. Issuance of the USBR ROW Grant is required prior to construction NTP. |
| Processing Time: | 6 to 9 months |
| Fees: | Initial administrative fee - $200. Additional environmental and realty processing fees are project specific. |
| Submittal: | Letter of request/Screening Analysis |
| When To Submit: | Design phase |
| Who Submits: | Project proponent |
| Who Receives: | Project proponent |
| URL(s): | http://www.usbr.gov/ |