Environmental Permit Matrix

Permit Details

Excavation Permit
Category:City of Las Vegas Permits
Issuing Agency:City of Las Vegas Development Services Center, 333 N. Rancho Drive, Las Vegas, NV 89106
Contact:Office: 702-229-6371
Regulated Activity:Underground construction on private property or within a City of Las Vegas ROW.
Prerequisite(s):No application. Must submit approved Barricade Plan and plans must be approved from plans check above. Barricade plan is approved by the Traffic Department. Must have County Dust Permit also.
Processing Time:Approximately 1 to 6 weeks
Fees:$5.00 per foot of excavation
Submittal:Approved barricade plan
When To Submit:Design phase
Who Submits:Contractor
Who Receives:Contractor
URL(s):http://www.lasvegasnevada.gov/Apply/permits.asp?id=5866#5866