| Category: | Federal Permits |
| Issuing Agency: | Nellis Airforce Base (NAFB), Main Gate, Craig Rd. and Las Vegas Blvd, Nellis AFB, NV |
| Contact: | Office: 702-652-7785 To check permit status: 702-652-2301 |
| Regulated Activity: | For construction on NAFB. For temporary activity and permanent use on NAFB. |
| Prerequisite(s): | Required prior to construction. Must file Air Force Form 103 (USA North Ticket Form). |
| Processing Time: | Temporary permit: 1 to 2 weeks. Permanent permit: 6 to 8 months |
| Fees: | No application fee |
| Submittal: | Air Force Form 103 |
| When To Submit: | Design phase |
| Who Submits: | Contractor |
| Who Receives: | Contractor |
| URL(s): | http://www.nellis.af.mil/ |