Base Civil Engineering Work Clearance Permit
Category:Federal Permits
Issuing Agency:Nellis Airforce Base (NAFB), Main Gate, Craig Rd. and Las Vegas Blvd, Nellis AFB, NV
Contact:Office: 702-652-7785 To check permit status: 702-652-2301
Regulated Activity:For construction on NAFB. For temporary activity and permanent use on NAFB.
Prerequisite(s):Required prior to construction. Must file Air Force Form 103 (USA North Ticket Form).
Processing Time:Temporary permit: 1 to 2 weeks. Permanent permit: 6 to 8 months
Fees:No application fee
Submittal:Air Force Form 103
When To Submit:Design phase
Who Submits:Contractor
Who Receives:Contractor
URL(s):http://www.nellis.af.mil/