Environmental Permit Matrix

Permit Details

Pipeline Crossing Agreement
Category:Utility Services Permits\Coordination
Issuing Agency:1.) Union Pacific Railroad (UPRR), Contract and Real Estate Department, 1416 Dodge Street, Room 1100, Omaha, NE 68179-1100 2.) 1800 Farnham St, Omaha NE 68102
Contact:John Devish Manager of Contracts Office: 402-544-8563
Regulated Activity:Activities crossing the UPRR ROW.
Prerequisite(s):UPRR and Project proponent negotiate agreement. Agreement must be signed by Project proponent General Manager and submitted by Project proponent to UPRR.
Processing Time:Permitting a Crossing: 30 to 45 days. Permitting Parallel Encroachment: 90 to 120 days
Fees:To Be Determined by UPRR
Submittal:Agreement Project
When To Submit:Design phase
Who Submits:Project proponent
Who Receives:Project proponent
URL(s):http://www.uprr.com/reus/encroach/encguide.shtml