| Category: | Utility Services Permits\Coordination |
| Issuing Agency: | 1.) Union Pacific Railroad (UPRR), Contract and Real Estate Department, 1416 Dodge Street, Room 1100, Omaha, NE 68179-1100 2.) 1800 Farnham St, Omaha NE 68103 |
| Contact: | John Devish Manager of Contracts Office: 402-544-8563 |
| Regulated Activity: | Drainage Modifications within a UPRR ROW |
| Prerequisite(s): | Engineering plans completed in accordance with the UPRR Drainage and Waterway Encroachment Planning Guide and Construction Procedures and a hydrology study according to the UPRR Drainage and Waterway Hydrology Study Guide |
| Processing Time: | Approximately 30 days – notification prior to survey or construction activities in UPRR ROW required. |
| Fees: | $1,055 application fee |
| Submittal: | Application, agreement, Hydrology Study, design drawings |
| When To Submit: | Construction phase |
| Who Submits: | Project proponent |
| Who Receives: | Project proponent |
| URL(s): | http://www.uprr.com/reus/drainage/procedur.shtml |