Environmental Permit Matrix

Permit Details

NPDES General Stormwater Permit for Construction
Category:Nevada State Permits
Issuing Agency:NDEP Bureau of Water Pollution Control 901S Stewart St., Suite 4001, Carson City, NV 89701-5249
Contact:Cliff Lawson, Stormwater Coordinator Office: 775-687-4670 Fax: 775-687-9448
Regulated Activity:Activity that will disturb 1 acre or greater, and will discharge storm water runoff from the construction site into a municipal separate storm water sewer system, or “waters of the US” as defined by Section 404 of the CWA.
Prerequisite(s):Permit issuance is required prior to construction/discharge activities. Preparation of SWPPP is required. Upon project completion, submit a Notice of Termination (NOT).
Processing Time:48 hours from receipt of the NOI
Fees:$200.00 filing fee and $200.00 annual fee. Permit fee is project specific
Submittal:NOI and SWPPP
When To Submit:Construction phase
Who Submits:Contractor
Who Receives:Contractor
URL(s):http://ndep.nv.gov/bwpc/storm01.htm
http://www.epa.gov/npdes/pubs/dmr.pdf
http://ndep.nv.gov/bwpc/ConstructionNOI/signin.aspx