Environmental Permit Matrix

Permit Details

Soils Report Submittal
Category:City of Las Vegas Permits
Issuing Agency:City of Las Vegas Development Services Center, 333 N. Rancho Drive, Las Vegas, NV 89106
Contact:Office: 702-229-6371
Regulated Activity:Soils associated with construction activity within a City of Las Vegas ROW (required for off-site construction projects).
Prerequisite(s):No application. Submitted with plans check and off-site construction permit request.
Processing Time:From 6 weeks up to 3 months
Fees:Included in cost of construction bond estimate for plans check
Submittal:Soils report and Plans and off-site construction permit request.
When To Submit:Design phase
Who Submits:Contractor
Who Receives:Contractor
URL(s):http://www.lasvegasnevada.gov/Apply/permits.asp?ID=5866#5866