| Category: | Federal Permits |
| Issuing Agency: | USBR Lower Colorado Region, P.O. Box 61470, Boulder City, NV, 89006-1470 |
| Contact: | Dave Curtis, Office: 702-293-8132 |
| Regulated Activity: | Required for short-term use of USBR land or USBR ROW. |
| Prerequisite(s): | A letter requesting right-of-use for proposed project segment within USBR Land is required. Applicant can apply as soon as there is a complete proposal, legal descriptions of project and alignment drawings. |
| Processing Time: | 60 days dependant upon scope of environmental and cultural issues. |
| Fees: | Initial administrative fee - $200. Additional environmental and realty processing fees are project specific. |
| Submittal: | Letter of request |
| When To Submit: | Design phase |
| Who Submits: | Project proponent |
| Who Receives: | Project proponent |
| URL(s): | http://www.usbr.gov/ |