Environmental Permit Matrix

Permit Details

USBR Right of Entry Temporary Use Letter
Category:Federal Permits
Issuing Agency:USBR Lower Colorado Region, P.O. Box 61470, Boulder City, NV, 89006-1470
Contact:Dave Curtis, Office: 702-293-8132
Regulated Activity:Required for short-term use of USBR land or USBR ROW.
Prerequisite(s):A letter requesting right-of-use for proposed project segment within USBR Land is required. Applicant can apply as soon as there is a complete proposal, legal descriptions of project and alignment drawings.
Processing Time:60 days dependant upon scope of environmental and cultural issues.
Fees:Initial administrative fee - $200. Additional environmental and realty processing fees are project specific.
Submittal:Letter of request
When To Submit:Design phase
Who Submits:Project proponent
Who Receives:Project proponent
URL(s):http://www.usbr.gov/