Environmental Permit Matrix

Permit Details

NEPA Decision Document (FONSI, Categorical Exclusion, or ROD)
Category:Federal Permits
Issuing Agency:Bureau of Indian Affairs (BIA), Environmental Quality Services, P.O. Box 10, Phoenix, AZ 85001 or MS-450, 400 N. 5th St., 14th Floor, Phoenix, AZ, 85004
Contact:Amy Heuslein, Environmental Protection Officer, Office:202-208-63710, Fax: 602-379-3833
Regulated Activity:Required for temporary or long-term use of tribal land.
Prerequisite(s):Agency coordination is required for all NEPA processes and documentation. Public involvement is required for some EAs and for all EISs.
Processing Time:Tiered EA- approximately 1 to 3 months for preparation and agency coordination. Longer for more complex projects. EA- approximately 6 to 8 months for preparation and agency coordination. Longer for more complex projects. EIS- approximately 12 to 18 months for preparation and agency coordination. Longer for more complex projects.
Fees:Project specific
Submittal:NEPA Document
When To Submit:Design phase
Who Submits:Project proponent
Who Receives:Project proponent
URL(s):http://www.doi.gov/bia/