| Category: | Nevada State Permits |
| Issuing Agency: | Nevada Department of Motor Vehicles and Public Safety, Nevada State Fire Marshall Division, 107, Jacobsen Way-Stewart Facility, Carson, City, NV 89711 |
| Contact: | Ginny Capucci, Program Assistant II, Office: 775-687-4290, Fax: 775-687-5122 |
| Regulated Activity: | Required for storage of 5 gallons or more of flammable liquid inside or 10 gallons or more of flammable liquid outside for 30 days or more. Also required for storage of 10 gallons or more of combustible liquid inside or 25 gallons or more of combustible liquid outside for 30 days or more. Roving Permit is needed if storage tanks will be moved to different staging areas on the project site. |
| Prerequisite(s): | The Hazardous Material Permit will be needed for onsite fuel storage during construction activities. The Roving Permit will be needed if storage tanks are moved to different staging areas as construction progresses. |
| Processing Time: | 2 weeks |
| Fees: | $150.00 per facility up to 2,000 lbs. of fuel. If over 2,000 lbs., then $250.00 |
| Submittal: | Notification |
| When To Submit: | Construction phase |
| Who Submits: | Project proponent |
| Who Receives: | Project proponent |
| URL(s): | http://fire.state.nv.us/hazmat.shtml |