Agendas
View Current Agendas
Search Historical Agendas
March TAC Meeting Cancelled
March CAC Meeting Cancelled
Technical Advisory Committee Agenda - March 30, 2017
Items
Item 03. Action to approve the minutes of the February 23, 2017 meeting (For possible action)
Item 04. Action to accept the financial reports (For possible action)
Item 05. Action to adopt amendments to the Ten Year Construction Program (For possible action)
Item 06. Action to accept the final accounting reports and closeout the interlocal contracts for the following projects (For possible action) -- C-1 Equestrian Tributary (construction) – HEN06F08
Item 06. Action to accept the final accounting reports and closeout the interlocal contracts for the following projects (For possible action) -- LVW-Grand Teton, Mountain Spa to Durango Drive (construction) – LAS22R12
Item 07. Receive the quarterly Project Status Reports: reporting period November 2016 through January 2017
Item 08. Discussion and possible action to approve the Prioritization of Projects, Ten-Year Construction Program and Fiscal Year 2017-18 project list (For possible action)
Item 09. Action to approve a request to reallocate funding within the interlocal contract for design for Fifth Street Collector, Centennial Parkway to Deer Springs Way – City of North Las Vegas (For possible action)
Item 10a. Action to approve the supplemental interlocal contracts for design and construction to extend the project completion date for the following projects (For possible action) -- Eighth Supplemental – North Railroad Conveyance – City of Boulder City
Item 10b. Action to approve the supplemental interlocal contracts for design and construction to extend the project completion date for the following projects (For possible action) -- Second Supplemental – Las Vegas Wash, Sloan Channel to Cedar Avenue – City of Las Vegas
Item 10c. Action to approve the supplemental interlocal contracts for design and construction to extend the project completion date for the following projects (For possible action) -- Eighth Supplemental – Gowan Outfall – Lone Mountain Branch (Rancho Drive to Decatur Boulevard) – City of Las Vegas
Item 10d. Action to approve the supplemental interlocal contracts for design and construction to extend the project completion date for the following projects (For possible action) -- Third Supplemental – Brooks Channel – City of North Las Vegas
Item 11. Action to approve the second supplemental interlocal contract for design to increase funding for Goodsprings – Phase I – Clark County (For possible action)
Item 12a. Action to approve the third supplemental interlocal contract for design to increase funding and extend the project completion date for Center Street Storm Drain - City of Henderson (For possible action)
Item 12b. Action to approve the second supplemental interlocal contract for construction to reallocate funding and extend the project completion date for Center Street Storm Drain - City of Henderson (For possible action)
Item 12c. Action to approve the second supplemental interlocal contract for construction to increase funding and extend the project completion date for Local Drainage Improvements for Appaloosa Storm Drain - City of Henderson (For possible action)
Item 12d. Receive a report on the award of bid for construction for Center Street Storm Drain and Local Drainage Improvements for Appaloosa Storm Drain - City of Henderson (HEN23B16)
Item 12d. Receive a report on the award of bid for construction for Center Street Storm Drain and Local Drainage Improvements for Appaloosa Storm Drain - City of Henderson (HLD06A15)
Item 13. Action to approve the first supplemental interlocal contract for maintenance for FY 2016-17 Maintenance Work Program – City of Henderson (For possible action)
Agenda Item Backup